2024 – Balder FPSO R6 riser pull in
Client: VÅR Energi
Vessel: Edda Freya/LDC Venturer
Period: September 2024
Task: Flexi Riser installation
Real Results:
Contingency diving assistance during flexi riser pull in.
Challenge:
ROV panel for DBSC operation too constricted for ROV.
Solution:
Onboard dive team modify panel to allow direct hydraulic connection.
Outcome:
FuncRiser successfully pulled in and secured.