2019 – ICCP repair & Thruster Change Hummingbird FPSO

Client: Teekay

Vessel: LDC Trust

Period: July-August 2019

Task: ICCP Repair

Real Results:
FPSO required in service change out of Thruster.

Challenge:
To change out in service photogrammetry and thruster change with mother vessel maintaining heading control.

Solution:
LDC dive spread mobilised on dual use heading control vessel.

Outcome:
Thruster replaced; photogrammetry performed.